[Ns-developers] Ns-3.7 Release Schedule (yes,that is ns-3.7)
craigdo@ee.washington.edu
craigdo at ee.washington.edu
Fri Sep 18 17:08:57 PDT 2009
Hi All,
In an attempt to remind everyone of how fast these ns-3 releases are
actually coming, and to try and get ahead of the game a little, I have
created an ns-3.7 release page for your viewing pleasure:
http://www.nsnam.org/wiki/index.php/Ns-3.7
Release pages are linked from the main wiki page, BTW.
The schedule is tentative at this time, but here it is:
1.October 14 -- ns-3.6 posted;
2.October 14 -- ns-3.7 Open phase begins;
3.November 18 -- Recommended cutoff for new feature submission;
4.November 25 -- Deadline for new feature submissions that require design
review;
5.December 2 -- Approved new feature ready-for-merge deadline;
6.December 9 -- Late merge period begins (Merge Week Begins);
7.December 16 -- Late merge period ends;
8.December 16 -- Open phase ends;
9.December 16 -- Maintenance phase begins;>
10.January 6 -- Maintenance phase ends;
11.January 6 -- Code freeze phase begins;
12.January 6 -- ns-3.7-RC1;
13.January 8 -- ns-3.7-RC2;
14.January 12 -- ns-3.7-RC3;
15.January 15 -- ns-3.7-RC4;
16.January 20 -- ns-3.7 posted;
17.January 20 -- Code freeze phase ends;
18.January 20 -- ns-3.8 Open phase begins.
Notice that the open phase for ns-3.7 starts in a little less than a month
and the recommended date for having a new feature ready to go in is a mere
two months from today. Also remember that we have many holidays coming up
that will eat into this schedule. I have pushed the schedule out slightly
to accommodate this.
If you would like to get your submission listed for ns-3.7, just email me
and I will begin actively maintaining the release page.
Regards,
-- Craig